Over the past six months, the FLASC team has made steady progress toward commissioning the FLASC HPES onshore pilot for grid qualification. We completed detailed engineering, finalised procurement of the main components and began receiving equipment on site, prepared the Plant One Rotterdam site, and progressed through the first stage of external verification with Bureau Veritas Group.
The major milestones achieved in the second half of 2025 are the following:
1. Design advancement and supplier collaboration.
Working hand in hand with our suppliers, we finalized detailed engineering of all major system components, ensuring that the design is scalable and transferable for future full-scale offshore deployment.
2. Preparation of the Plant One Rotterdam BV site.
We assessed the site upgrade requirements, completed final engineering designs for installation, procured all necessary components, and performed the physical installation work. This included electrical cabling, installation of power cabinets, floor reinforcement, and safety-related structural partitioning, bringing the site to readiness for further pilot assembly.
3. Completion of first part of external verification by third-party certifier.
Bureau Veritas completed the initial certification phase, confirming that our overall system design meets the required standards before physical assembly begins.
4. Team operational readiness.
All required personnel safety and operational trainings have been completed: VCA (workplace safety) certification, forklift (heftruck) training, and compliance with NEN 3140 for safe operation and maintenance of low-voltage electrical installations. These certifications ensure that all on-site work can proceed safely and responsibly.
5. Start of equipment delivery.
This marks the transition from design and planning into the execution phase enabling us to begin assembly and system integration in the coming months.
During Q1 2026, we will begin the mechanical and electrical assembly of the pilot plant, complete the physical installation and integrate all system components. We will commence system testing and progress toward grid qualification and performance validation by DNV and Bureau Veritas Group.
Moving into Q2, once the qualification phase is successfully completed, the pilot plant will be used for further extensive testing and be ready to welcome external stakeholders for on-site visits.
This project is supported by European Innovation Council and SMEs Executive Agency (EISMEA).